• Complete epoxy protective system for hazardous material storage areas.
• Full surface preparation and sanding of walls and floors.
• Application of epoxy primer.
• Application of epoxy putty for surface leveling.
• Application of epoxy intermediate coating.
• Final application of polyurethane protective topcoat for chemical and abrasion resistance.

The storage areas were very high in elevation, with large wall surfaces that required complete sanding and coating. Working at height increased execution complexity.
Specialized access and sanding equipment were used for high wall areas, followed by careful multi-layer application of the epoxy and polyurethane system. The project was completed successfully, delivering a fully sealed and durable protective system for hazardous storage.